|
[Abstract]
In view of that the average electricity consumption
per capita is still rather low in China,
this paper puts forward ten focal problems
in the 10th Five-Year Power
Plan, including optimized allocation of
power sources and power networks,
environmental protection in coal-fired
power plants, as well as localization of
power equipment, etc.
[Keywords] the 10th
Five-year Plan
power industry in China
power planning
power construction
It is universally acknowledged that great progress
was made in China electric power industry
during the 9th Five-year Plan
period. The continuous shortage of
electricity in the last 20 years has been
turned round. In 2000, the nationwide
installed capacity reached 319 GW with an
annual average increase of 8%. The
electricity generation reached 1368.5 TWh,
increased by 8% annually. The annual
average increase of GDP was 8.3%. The
power elasticity was 0.76, close to the
average value of 0.8 from 1981 to 2000.
Even so, the average electricity consumption per
capita in China is still rather low, far
lower than that in the developed
countries, and even a wider gap exists as
compared with the world average level. The
planned annual increase of GDP is about 7%
in the 10th Five-year Plan
period. As the estimated power elasticity
is 0.8, power demand and installed
capacity in 2005 will reach about 1800 TWh
and 400 GW respectively, and 2350 TWh and
520 GW respectively in 2010. In order to
realize these targets, the power industry
needs to be developed fast, and great
attention should be paid to ten focal
problems.
Focus One:
With less power source construction projects carried over, the areas
short of power supply will be increased in
the early 10th Five-year Plan
period.
The new generating capacity to be installed in the 10th
Five-year Plan period will be 80 GW.
Together with the retrofit capacity
(totaling 15,000~20,000 MW) with
substitutions of large size units for
small ones and coal units for oil ones,
the total capacity to be newly
commissioned will reach about 100 GW,
about 20,000 MW annually. Due to the
construction period of large generating
project is relatively long, it is
necessary to keep a certain construction
scale to meet the increasing demand of
electricity consumption. At the end of
2000, the total capacity of the power
networks in China was 319.32 GW, among
which hydropower was 79.88 GW, thermal
power 237.54 GW and nuclear power 2.1 GW.
The total capacity under construction was
60.02 GW, among which hydropower was 26.05
GW, thermal power 27.37 GW and nuclear
power 6.6 GW.
There exist two main problems. (1) The construction
scale of power networks is far
insufficient in South China, East China
and North China where power supply could
originally meet the demand basically but
now appears insufficient. The capacity to
be commissioned in the early 10th
Five-year Plan period will not be enough
to meet the increasing demand of power
consumption. Power shortage areas will be
increased. Guangdong, Zhejiang and South
Hebei power grids, which are now
experiencing a power shortage, will get
into an even more serious situation. Power
shortage will emerge in Jing-Jin-Tang,
Shanghai, Jiangsu, Shandong, Guangxi and
Ningxia power grids in 2002 or 2003.
Therefore, a batch of thermal power
projects needs to be started to construct
urgently.
(2) The construction scale of hydropower is seriously
insufficient. Deducting 18,200 MW of the
Three Gorges from the total number, the
total capacity of other hydropower
stations under construction only amounts
to 7850 MW. About 15,000 MW can be put
into operation in the 10th
Five-year Plan period, obviously too
little to meet the requirements of Western
Region Development and sustainable
development. A batch of large and medium
scale backbone projects needs to begin to
construct immediately in the 10th
Five-year Plan period, such as Longtan,
Xiaowan, Gongboxia, Pubugou, Suofengying,
Sanbanxi and Shuibuya hydropower stations
as well as Tongbai, Yixing, Tai’an and
Zhanghewan pumped storage hydropower
stations. As a result, 20,000 MW would be
expected to put into operation in the
period. In addition, hydropower stations
like Goupitan, Nuozhadu, Jinping Cascade I
and Jishixia (or Laxiwa) are striven to
begin construction in the late 10th
Five-year Plan period.
Focus
Two:
Large
amounts of oil-fired units need to be
substituted for coal-fired units. The
scope and amount of technical retrofit is
broad and huge.
There are two main aspects: (1) 20000 MW medium- and
low-pressure units with high coal
consumption and serious pollution will be
replaced with large-sized units. (2)
Oil-fired units will be substituted by
large size coal-fired ones. In 1999, there
were oil-fired units totaling 18,300 MW,
with electricity generation of 46.8 TWh
and oil consumption of 13.6 Mt.
There weren’t many small units shut down in the
past two years. This implies that
retrofitting of small units needs to be
speeded up in the 10th
Five-year Plan period. For example, during
the 10th Five-year Plan period,
small thermal units of 10,000~15,000 MW
will be retrofitted, 5000 MW oil-fired
units will be substituted by coal-fired
ones, besides, another 15,000~20,000 MW
coal-fired units need to be newly added.
In order to reduce the import of oil, it
is better to use natural gas in the areas
where possess natural gas.
Moreover, some enterprises have their own industrial
diesel units, since oil is expensive, and
power supply from grids is cheap, it is
necessary to enhance the power generation
and supply capabilities of grids for
meeting enterprises’ power demand so as
to reduce the oil consumption of diesel
units.
Focus
Three:
Large
size backbone hydropower stations with
better regulation performance must be
exploited with priority.
China has exploitable hydropower capacity of 378 GW
with electricity generation of 1920 TWh.
Among them, 72.6% is located in the west
part of China. Most of hydropower stations
in the eastern and central regions with
better conditions have been well
developed, except Shuibuya on Qingjiang
River. In the future, focal points of
hydropower development should turn to the
west part of China. Since the power
consumption in the western region is
small, and with the great difference of
output between high water period and low
water period, generally, the firm output
in low water period is only about 30% of
the installed capacity. It is difficult to
make full use of the power generated
during high water period. There is no
doubt that it is a restriction on the
development of hydropower. Therefore, it
is suggested that, (1) to give precedence
to the exploitation and utilization of
backbone hydropower stations with larger
reservoir capacity, better regulation
performance and greater amount of
electricity generation in low water
period, such as Longtan, Xiaowan, Pubugou,
Jinping Cascade I, Sanbanxi and Hongjiadu,
etc., so as to raise the generating
capability in low water period. (2) to do
well the plan and implement the strategy
of Sending Power from West to East, and
send power to the eastern coastal areas
where power consumption increases quickly.
Focus
Four:
The
proportion of gas-fired power generation
will be increased. The localization of
large-scale gas turbine will put on
schedule.
Along
with several gas transportation pipe lines
(including lines from Tarim to Shanghai,
Qinghai to Xining and Lanzhou, Sichuan to
Hubei and Hunan, etc.) for “sending gas
from west to east” to be built and put
into operation, natural gas fields
exploited successfully on the East China
Sea and the South China Sea, and liquified
natural gas imported from abroad in
Guangdong, some portion of natural gas
will be used for power generation.
According to statistics and predictions by certain
departments, the consumption of gas by
power generation is as follows: the
consumption in 2000 was 3.3 billion m3,
representing 12.5% of the total. In 2015,
it will be 23.5 billion m3,
representing 29.7%. In 2020, it will be
63.5 billion m3, representing
40.7%.
From the above, it is concluded that there will be a
rapid growth in gas-fired electricity
generation. Some steamgas
combined cycle power plants and
cogeneration power plants will be built in
Shanghai, Zhejiang, Jiangsu, Guangdong,
Guangxi, Hainan, Beijing and Lanzhou.
Except the areas where gas price is low,
the cost of generation by natural gas will
be slightly higher than that of coal-fired
plants with FGD. But it is good for
improving the environment conditions and
peak regulation capability of power
network, as well as raising the
reliability of power supply. Affected by
the limitation of energy supply and the
raising of gas price which will come up
probably in the future, the proportion of
gas-fired power generation in power mix
won’t be high.
Lack
of experiences with large gas turbine
production in China, such equipment needs
to be imported at first, and it is better
to use similar types of units. The import
of equipment and introduction of
manufacturing technique shall be carried
out simultaneously. While negotiating and
exchanging with foreign sides, more
efforts should be arranged on
self-developing research so as to realize
the localization of gas turbine
fabrication as soon as possible.
Focus
Five:
Attach
importance to environmental protection of
coal-fired power plant, and realize the
sustainable development strategy.
In 2000, the nationwide total capacity of coal-fired
power plants reached 219.2 GW, accounting
for 68.7% of the total installed capacity,
their electricity generation was 1060 TWh,
making up 77.5% of the total. It is
predicted that 60~65% of the newly-added
capacity in the future will still be
coal-fired thermal power. In the 10th
Five-year Plan period, coal consumption by
power generation will increase by 150 Mt.
It is necessary to keep balance between
coal supply and consumption. Power plant
construction and layout shall conform to
market economy law and pit-head, roadside
and port power plants shall be properly
planned to build. In order to implement
the strategy of Sending Power from West to
East, a batch of large scale pit-head
power plants will be built in Shanxi, West
Inner Monogolia, Shaanxi, Ningxia, Guizhou
and Yunnan to send power to load centers
like Jing-Jin-Tang, Shandong, East China
and Guangdong etc. In order to protect our
environment and realize sustainable
development strategy, we must devote more
efforts to research and solve
environmental protection problems in
coal-fired power plants, and develop clean
coal power generation technology.
300~600
MW subcritical and supercritical units
with high efficiency and energy saving
performances should be adopted to reduce
fuel consumption and pollutant emission.
Most of the newly built power plants will
be equipped with FGD or CFBC boiler to
meet the emission standards. Old power
plants that haven’t come up to the
environment standards must be retrofitted
or shut down. Cycling operation capability
and thermal efficiency of thermal power
plant must be raised.
Focus
Six:
Domestically
made 1000 MW class PWR nuclear units will
enter trial-producing stage.
Three nuclear power plants, Ling’ao, Qinshan and
Lianyungan, which are under construction
now, will be put into operation in the 10th
Five-year Plan period, and there will be
no other nuclear power projects to be
planned then. The amount of energy
resources per capita is not much in China.
From the point of view of long term energy
balance, it is necessary to develop
nuclear power. Only 1000 MW class nuclear
power plant can achieve economic scale,
and the tariff of electricity will be
competitive. China now has grasped the
manufacturing technology of PWR,
trial-production is needed to clearly
carry out in the 10th Five-year
Plan period, and new project construction
should be arranged so as to keep the
sustainable development of nuclear power
industry in China.
Focus
Seven:
Vigorously
expand power networks, speed up
interconnection between provinces
Power
networks and inter-provincial
interconnection will be greatly developed
in China during the 10th
Five-year Plan period. After the Three
Gorges Hydropower Station being put into
operation, the middle part network
stretching eastward to Shanghai and
westward to Chongqing and Sichuan will be
initially established, and HVDC
transmission project from the Three Gorges
to Guangdong will also be built for
transmitting 3000 MW power to Guangdong.
The surplus electricity of Ertan
Hydropower Station and other hydropower
stations in Sichuan during high-flow
period could be sent eastward to the East
China Power Network through the surplus
transmitting capabilities of the Three
Gorges power grid. The Southern
Interconnected Power Network will increase
its sending capacity to 9,000 MW through
the constructions of
Tianshengqiao-Guangdong HVDC transmission
and substation project, the third circuit
from Tianshengqiao to Guangdong, the 500
kV double-circuit transmission and
substation project from Anshun to Liuzhou
to Guangdong, as well as HVDC transmission
project from Guizhou to Guangdong.
Meanwhile, the construction of the 500 kV
transmission and substation project from
Xinxiang, Henan to Handan, Hebei, which
will be speeded up, will realize the
interconnection of the Central China Power
Network with the North China Power
Network. The North China Power Network and
the Northeast China Power Network will be
interconnected through the construction of
the 500 kV project (in operation) from
Jiangjiaying, Hebei to Suizhong, Liaoning,
and Fujian Power Grid will be connected
into the East China Power Network through
the construction of the 500 kV project
from Fuzhou to Jinhua, Zhejiang. 500 kV
and 330 kV systems in each power networks
will be continuously stretched and
enhanced, forming initially three large
interconnecting power networks involving
the southern part, the central part and
the most area of the northern part. With
advantages of less capital cost, shorter
construction period and better benefit, AC
synchronized interconnection which is
widely used in the eastern power network
of North America and the networks in West
Europe should be adopted in China. As a
contrast, DC interconnection will restrict
the benefit of interconnection.
Simultaneously, measures for raising the
transmitting capabilities of 500 kV line
should be actively investigated and
applied so as to create the conditions for
fully utilizing hydropower and reasonably
allocating thermal power, or, to prompt
the optimized allocation of resources. In
addition, the 750 kV transmission line
from Gongboxia to Lanzhou, which will be
first operated at a dropped voltage of 330
kV, will be constructed. The feasibility
and necessity of expanding the applied
scope of 750 kV will also be studied.
Focus
Eight:
Promoting
actively equipment localization
The
technological level in electric power
industry will improve significantly during
the 10th Five-year Plan period.
Therefore, equipment localization will be
promoted actively in the period.
Localization will be advanced by way of
combining imported technologies and
domestic research and development. The
problems existing in the localization of
some equipment will be resolved in the
period. These include super critical
pressure large size thermal generating
unit, million kW class nuclear power
generating unit, large size hydropower
unit, large size pumped-storage unit,
large size gas turbine, large size
circulating-fluidized-bed boiler, wind
power generating unit, desulfurization and
denitrogen equipment in thermal power
plant, environmental protection equipment,
DC transmission facilities, 750 kV
ultra-high voltage transmission and
substation equipment, etc. Localization of
stabilizing equipment, advanced
distribution equipment, power plant
automation equipment, as well as
dispatching and communication automation
equipment of power networks will be
improved further.
Focus
Nine:
Considering
generation, transmission and distribution
simultaneously in power planning
Power
industry features that electricity
generation, transmission, distribution and
consumption are finished simultaneously,
therefore, generation, transmission and
distribution must be planned at the same
time. Power planning bases on power
consumption increase, which must be paid
great attention. For long ages, an
important experience but also a common
practice in power planning has been to
optimize the allocation of power sources
and power networks based on survey on
power consumption and increase prediction
on power capacity and generation.
Whichever aspect should not be
unilaterally and separately given
prominence to. Power planning method after
power plant is separated from network in
administration is worth to be studied
seriously.
Focus
Ten:
Realizing
the program of Sending Power from West to
East with unitive knowledge and teamwork.
In
view of that Sending Power from West to
East is one of the most important
constituents in Western Region
Development, and so is in its advantages
conversion from resource into economy,
accelerating hydropower development and
utilization, as well as realizing the
strategy of sustainable development. It
should benefit both eastern and western
regions based on the market rules.
Electricity sending and receiving parties
should unify their knowledge from the
altitude of getting rich together for both
eastern and western regions, enter into
the problems and difficulties of the
opposite party, frame the plan practically
and realistically and solve the problems
occurring during implementation. They
should also sign duly long-term contracts
of electricity sales and tariff so as to
decrease risks for the both parties. The
program of Sending Power from West to East
would be realized successfully based on
these important considerations.
|