YOUR  PLACE : Home>>Project under construction>>                                
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   
Project under construction

2002

1999

 

Commissioning projects schedule of SP in 2002 

Type of planning

Schedule

Projects name and installed capacity

Thermal power, Nuclear power

planning committing 21 units with the capacity of 6850 MW

starting-up and trial operation for the complete unit Qinshan nuclear
phase 2  No.1
600MW
   
finish igniting Xutang No.1
300MW
   
finish acid cleaning of boiler Qitaihe No.2
350MW
   
finish hydraulic test of boiler Jixian phase 2 No.4
600MW
Jixi No.1
100MW
Fushun phase 2 No.1
200MW
Yangchen No.5
350MW
Jiujiang phase 3 No.1
350MW
Heze phase 2 No.2
300MW
Dezhou phase 3 No.1
660MW
   
finish erection of boiler component Jixi No.2
100MW
Yangchen No.6
350MW
Pucheng phase 2 No.3
330MW
  Dezhou phase 3 No.2
660MW
Liaocheng No.1
600MW
Laicheng No.3
300MW
  Baoding No.1
125MW
Baqiao No.1
100MW
Xutang No.2
300MW
start erection of boiler component Shenyang No.5
50MW
Baoding No.2
125MW
 
making effort to commit finish erection of boiler proper Shizuishan phase 2 No.1
300MW
Laicheng No.4
300MW
 

Hydropower

  finish rotor hoisting Dachaoshan No.2
225MW
   
  finish parts assembling Tuolin No.2
120MW
Dachaoshan No.3
225MW
 
   finish 2st phase concreting Dachaoshan No.4
225MW
Hongjiang No.1
45MW
 

    * (1)The single generating unit capacity listed in the table is above 20 MW for hydropower and 50 MW for thermal power . (2)The statistics are contributed by Dept. of Power Source Construction, State Power Corporation on January 7,2002

All Rights Reserved, Copyright(C) 1997-2001, State Power Corporation of China.