2003 was the first year after implementing the
Program of Power Institutional Reform put forth by the
State Council, with the separation of power plants from
power grids and reorganization of the state-owned power
assets basically completed. Under the correct leadership
of CPC Central Government and the State Council, the
power institutional reform progressed smoothly and
power systems operated stably.
Driven by sustained rapid growth of national
economy, both electricity generation and consumption
in China had the tendency of parallel rapid increase in
2003, a year with fastest growth rate since open and
reform policy. In this year, the national electricity generation
amounted to 1905.2 TWh, or 15.17% higher than
the previous year; and the electricity consumption of
the whole society amounted to 1889.1 TWh, or 15.29%
higher than the previous year. The nationwide power
shortage situation, however, became more and more
severe, twenty-two provinces (autonomous regions,
municipalities) suffered from load curtailments, in
which, the most severe regions included Zhejiang,
Jiangsu, Shanghai, Yunnan, Guizhou, Hebei (southern
area), Shanxi, Inner Mongolia (western area), etc. Dealing
with this rigorous power supply situation, under the
unified disposal of the State Council, all related units
had made concerted efforts and taken effective measures
to alleviate power shortage situation and safeguard safe
and stable operation of the power system.
In line with accelerated power constructions, a
batch of key power projects proceeded smoothly. By
the end of 2003, the national total power installed
capacity hit 391.4 GW, or 9.77% increase over 2002. The
world renowned Three Gorges Project duly realized the
three tremendous targets water storage, navigation
and power generation. There were six units put into
operation in succession by the end 2003, which made
the total installed capacity to 4200 MW and an accumulated
electricity generation of 8.607 TWh, created
a world record of installation and commissioning for
hydropower units. The projects of power transmitting
from west to east, mutual complementary between north
and south and national power grid interconnection,
including a batch of key projects such as the DC transmission
project from the Three Gorges to Changzhou,
the Three Gorges AC transmission and substation phase
II project, the DC transmission project from the Three
Gorges to Guangzhou, the interconnection project
between Central China and North China power grids,
the interconnection project of the second circuit between
Fujian and East China power grids, the Tokto power
send-out phase I project, the 500 kV AC transmission
and substation project from Guizhou to Guangdong,
etc. all were successfully commissioned.
In 2003, the power environmental protection and
resources conservation were further enhanced. The State
started a new pollution charging system, and revised
and issued the Emission Standards of Air Pollutants
for Thermal Power Plants. The related governmental
departments issued new requirements on SO2 control
for coal-fired power plants. The electric power industry
and power enterprises placed higher priority on environmental
protection and resources conservation; the
power capacity newly equipped with flue gas
desulfuration equipment broke through 10 GW, which
opened the prelude of equipping flue gas desulfuration
equipment on a large scale.
|